Growth Plans – Generation

growth plan
* MW – Mega Watt
Capacity Addition- Projects under construction

Sl. No. Project Capacity (MW)
1 Raghunathpur TPS Phase-I Unit No. 1 (1×600 MW)
[Location: Raghunathpur, Dist. Purulia,West Bengal]
600
2 Raghunathpur TPS Phase-I Unit No. 2 (1×600 MW)
[Location: Raghunathpur, Dist. Purulia,West Bengal]
600
3 Bokaro ‘A’ TPS (1x 500) MW
[Location: Bokaro Thermal, Dist. Bokaro,Jharkhand]
500
4 Raghunathpur TPS Phase-II Unit No. 1 (1×660 MW)
[Location: Raghunathpur, Dist. Purulia,West Bengal]
660
5 Raghunathpur TPS Phase-II Unit No. 2 (1×660 MW)
[Location: Raghunathpur, Dist. Purulia,West Bengal]
660
TOTAL 3020 MW

 

Capacity Addition- Future Plan

Sl. No. Project Location Capacity (MW)
1 Koderma TPS Phase-II District- Koderma
Jharkhand

1600 (2x 800)

2 DTPS (in place of existing old Units-1,2&3) District- Barddhaman
West Bengal

660 (1x 660)

3 CTPS (in place of existing old Units-1 to 6) District- Bokaro
Jharkhand

1320 (2x 660)

4 Renewable Energy- Solar Power Plant West Bengal / Jharkhand 1000 (in phases)